Month: August, 2010
Construction Update – 083110
- August 31, 2010
- posted in: Construction
- No comments yet
We’re almost there! Just 6 more days before school starts – don’t worry, we’ll be ready. The old building is entirely dismantled and most of the pieces have been removed. The new, temporary modulars are on-site and assembled, and Mr. Shimo is hard at work hooking the decks back up to them.


Half of Mrs. Melvin's old room
further change in school start date!
Updated Good News!
Great progress is being made in setting up our temporary modular classrooms for the start of this school year!
Unfortunately for us, the contractors are running a bit behind. We have put pressure on them to make sure that everything is up to Fell’s standards and that is taking some additional time. We want to make sure that everything is up to speed to start. That being said, we are making our final adjustment to the start of this school year.
All students, grades Kindergarten through eight, will start school on the 7th of September, and we will have full days for everyone. This moves school back one week. We will plan our Open House once school gets back and we get everyone settled.
It will be an eventful and event-filled year at Fell!
See you all on Sept. 7th bright and early for full days!
Read moreConstruction Update – 081810
- August 18, 2010
- posted in: Construction
- No comments yet
The pieces of the old building are about to be removed from the property, and temporary modulars that will be our homes during the next year are arriving! By the end of the week the temporary modulars should be in-place and assembled.
Only one week to go before the start of school, and we’ll be ready!

Construction Update – 080910
- August 9, 2010
- posted in: Construction
- No comments yet
The dismantling continues, with real progress being made!

Dismantling Continues
- August 5, 2010
- posted in: Construction,News & Events
- No comments yet
As you have hopefully already heard, the beginning of school has been pushed back one week so that we can have the old building off the site in before classes resume. We’re making progress!

Front of the building, with tow-hitches in place.
change in school start date!
- August 4, 2010
- posted in: IMPORTANT,News & Events,Principal
- No comments yet
Dear Parents and Community Members,
In our on-going effort to assure a safe and happy return to our 2010-2011 school year and in anticipation of building our new building, the School Board voted last night to delay the start of school by one week. Therefore we will have students in grades 1 through 8 return to us on Monday, August 30th, starting at 7:45 a.m. and ending at 11:00 a.m. Kindergarten students will report to us on Wednesday September 1st from 7:45 a.m. to 11:00 a.m. The week of August 30th will be half days with dismissal each day at 11:00.
Beginning Tuesday, September 7th, all grades begin full days of school.
We appreciate your patience as we finalize preparations for a new building site.
Mary Jo Walsh, Principal
Read more2010-2011 academic calendar
- August 2, 2010
- posted in: IMPORTANT,News & Events
- No comments yet
The 2010-2011 Academic Calendar is now available for download. Please pay particular attention to the first week of school; Grades 1-8 begin on August 23rd, while Kindergarten begins on August 25th. The first week is entirely half-days, as usual.
2010-2011 Academic Calendar